Main Road Bridge Replacement #4 - February 9, 2018

Friday, February 2, 2018: It was determined that a gas line was in the way of the footings for headwalls, and Zia Natural Gas Company was contacted.  They made the decision that the line could be relocated, and in an effort to expedite the process, Roper Construction would do the digging, and then Zia Gas would move the gas line on Tuesday 2-6-18.